Canada’s battery market is taking shape province by province, and Ontario is moving fastest.
Canada had 552 MW of grid-connected storage projects larger than 1 MW at the end of 2024. In a July 2025 snapshot, the Canada Energy Regulator said projects already under construction could lift that to 1,149 MW by 2030. If every approved project goes ahead, the figure could reach 2,768 MW. Batteries are the country’s fastest-growing storage technology, and every project then under construction used batteries.1
Even that national figure does not show how quickly the next wave is arriving. By September 2026, six reported front-of-meter battery plants in Ontario, Oneida, Napanee, Hagersville, Sanjgon, York and Goreway, added up to about 1,050 MW. This is our total from named projects. No official national total is available for comparison. It does not include batteries behind the meter, Alberta’s merchant fleet or smaller systems.
Batteries now do much more than support renewables. They are becoming system capacity. They can react in fractions of a second, store power when it is cheap and release it when it is valuable, provide operating reserves and sometimes delay new grid investment. Ontario buys these services through long-term contracts. Alberta relies more on merchant revenues and grid-support services.
The market is moving fast
Canadian grid-connected storage
MW · projects >1 MW“2030 build” covers 12 projects under construction. “2030 upside” assumes another 27 approved projects also open. These figures show possible outcomes rather than guarantees. Source: CER market snapshot republished by Energi Media.1
Industry forecasts are higher. CanREA expects 12 to 16 GW of new energy storage by 2035, part of a wider CA$205 billion opportunity in wind, solar and storage.14 Energy Storage Canada says the country needs 8 to 12 GW to support its net-zero goals.15 Grand View Research, a commercial forecaster, expects Canadian BESS revenue to rise from US$586.8 million in 2024 to US$2.9 billion in 2030, a 31.7% CAGR.16
Why batteries are growing
IESO expects Ontario electricity use to rise 75%, from 151 TWh in 2025 to 262 TWh in 2050. Summer and winter peaks could be nearly equal by 2030.2
Pickering is not closing. Its four remaining units are being taken offline in September 2026 for a $26.8 billion refurbishment. Unit 5 is expected back in 2031, with all four returning in stages by 2034. The multi-year outage creates a supply gap that batteries can help cover through the early 2030s.2223
Ontario’s higher forecast includes EV supply-chain factories, AI data centres, population growth and wider use of electricity across the economy.2
The federal Clean Technology ITC can cover up to 30% of the capital cost of qualifying stationary storage through 2033, if labour conditions are met.11
BNEF’s 2025 survey put stationary-storage packs at US$70/kWh, down 45% in one year. Four-hour turnkey systems averaged US$110/kWh worldwide.13
Ontario’s long-term IESO agreements give projects a steady source of capacity revenue. Wholesale trading and operating reserves can add more income.5
The federal Clean Electricity Regulations were finalized in December 2024. They aim for a net-zero electricity system by 2050 and bring in an emissions standard for larger fossil-fuel generators through the 2030s. Federal strategy documents say the rules should encourage investment in non-emitting resources, including batteries.12 Provinces do not agree on the policy. Alberta publicly rejected an earlier draft. That means investors still need to study the rules in each province.
Ontario leads the way
Ontario has run several rounds of battery contracts. This has built a large project pipeline and shown the market what storage capacity is worth. Newer rounds also call for batteries that can run longer and projects with more Indigenous ownership.
More competition has pushed prices down. The reported average winning price fell from CA$881.09/MW in E-LT1 to CA$672.32/MW in LT1, a drop of 24%.46 LT2 capacity prices were reported at 36% below E-LT1 and 16% below LT1. Its three winning projects will use eight-hour batteries, have 20-year contracts and must be in service by 1 May 2030.7 Next comes the Long Lead-Time RFP. It targets up to 800 MW of long-duration storage under 40-year contracts.3
Local support and Indigenous ownership now matter in the bidding process. All three LT2 winners had municipal backing and at least 50% First Nations equity.7 Oneida, Hagersville, Skyview 2 and Nova Scotia’s three-site program also have Indigenous partners. In Canada, these partnerships are becoming an important part of whether a project can get financed and built.
Projects to watch
Hagersville
Haldimand County, Ontario300 MW / 1,200 MWh
Boralex developed the project with Six Nations of the Grand River Development Corporation. It was commissioned in March 2026 with 334 Tesla Megapack 2XL units. At the time, it was reported as Canada’s largest operating battery.8
Oneida
Haldimand County, Ontario250 MW / 1,000 MWh
Oneida began commercial operation on 7 May 2025, ahead of schedule and below its estimate of about CA$800 million. Northland reported a final cost of about CA$700 million. The project has a 20-year IESO capacity contract and Indigenous equity partners.9
Napanee
Greater Napanee, Ontario250 MW / 1,000 MWh
Atura Power led this project. It began operating in May 2026, about five weeks early and under its CA$600 million budget. Sources disagree on whether it belongs to LT1 or E-LT1, so we have not named the procurement round here.17
Skyview 2
Edwardsburgh Cardinal, Ontario411 MW / 1,858 MWh
Potentia Renewables is developing Skyview 2 with the Algonquins of Pikwàkanagàn First Nation. It is under construction and is expected to begin commercial operation in Q2 2027. It is Canada’s largest contracted battery project.10
Nova Scotia Power BESS
Bridgewater, Waverley & White Rock150 MW / 705 MWh DC
Three 50 MW sites opened on 16 and 17 September 2026. The CA$354 million program includes financing from the Canada Infrastructure Bank, a CA$116 million federal grant and Mi’kmaw equity through WMA.18
Enfinite eReserve
Northern Alberta9 sites / up to 315 MWh
This merchant fleet provides balancing and frequency-regulation services. All nine sites were dispatched during Alberta’s January 2024 grid emergency. The event showed how quickly batteries can respond, even without Ontario-style contracts.19
Two ways to earn revenue
Ontario
- Long-term IESO capacity contracts
- Revenue from buying and selling power
- Operating reserves and other grid services
- Municipal support and Indigenous equity matter more with each round
Alberta
- More exposure to market prices
- Revenue from frequency regulation and fast response
- No Ontario-style long-term capacity contract
- Revenue can move more sharply, in either direction
Oneida earns money in three ways. It receives a fixed capacity payment under its IESO agreement, sells energy into the wholesale market and provides operating reserves and other grid services.5 Alberta’s eReserve fleet earns money by responding to the AESO market, where speed and changing prices matter more. Investors should not treat every Canadian storage project the same. Contract length, dispatch rights, local grid limits and competition for grid services all need to be checked province by province.
What could slow things down
Battery prices are falling and contracts are getting easier to finance. The tougher issues are finding suitable sites, connecting projects to the grid, addressing fire-safety concerns, building enough transmission and setting fair rules for smaller batteries.
- Community supportA proposed 4.99 MW LFP project in Armour Township received 1,508 submissions against it and only two in support at a November 2025 meeting. Council rejected the project and the developer appealed. The township later dropped its legal fight after warning that the legal costs could be high.20
- Grid connection delaysWe found no reliable Canada-wide figure for BESS queue delays. This gap matters because an approved project may still take years to connect and begin operating.
- Revenue for smaller systemsOntario had roughly 225 MW of large C&I behind-the-meter batteries in 2023, based on an older estimate. Energy Storage Canada says those systems are still underused. It has proposed an 8 to 10 year standard-offer program for 100 to 500 MW.3
- Longer-lasting batteriesOntario is moving from four-hour systems to eight-hour LT2 projects. It is also planning to buy up to 800 MW of long-duration storage. The technologies that win, and the cost of financing them, will shape the next round of growth.
The next milestones are clear. Skyview 2 and other LT1 projects are due to enter service from 2027. The three eight-hour LT2 projects are due by May 2030, and the first long-duration projects will come from the LLT process. The opportunity through 2035 is much larger, but these projects still have to be financed, connected and built.
The bottom line: Canada is investing in batteries because they solve several grid problems. They can cover capacity gaps, support variable generation, respond faster than thermal plants and earn money from several grid services. Low-cost cells alone will not decide which projects succeed. Developers also need a grid connection, lasting local support, strong Indigenous partnerships and a revenue model that fits the province.
Sources
- Canada Energy Regulator market snapshot, republished by Energi Media, 23 July 2025.
- IESO, 2025 Annual Planning Outlook.
- Energy-Storage.news, Ontario storage and supply outlook.
- Energy-Storage.news, E-LT1 results.
- Electrical Business, Oneida revenue model.
- Energy-Storage.news, LT1 results.
- Ontario release, LT2 capacity results.
- ESS News, Hagersville commissioning.
- Northland Power, Oneida commercial operations.
- ESS News, Skyview 2 groundbreaking.
- CPABC, Clean Economy Investment Tax Credits.
- Natural Resources Canada, Powering Canada’s Future; EnergyNow, provincial response and Jason Dion quote.
- Energy-Storage.news, BNEF 2025 battery price survey.
- Solar Builder, CanREA 2035 study.
- Mobility Foresights, quoting Energy Storage Canada.
- Grand View Research, Canada BESS revenue forecast.
- Cozzy Energy Solutions, Napanee commissioning (secondary source).
- Energy-Storage.news, Nova Scotia BESS program.
- Energy Storage Pro, Enfinite eReserve fleet.
- Canadian Underwriter, Armour Township opposition; Village Media, township drops appeal fight.
- Sustainable Biz Canada, Ontario storage surge and NextStar pivot.
- The Global Press Network, Pickering refurbishment advances, 21 September 2026.
- Vivid Communications, Pickering nuclear refurbishment, 25 September 2026.
Research cut-off: 26 September 2026. Monetary values are Canadian dollars unless marked US$. Project status and policy details are dated snapshots; re-verify before investment or procurement decisions.
↑ Back to topA note on the figures: No verified Canada-wide MW/MWh total is available for 2025 to 2026. The 552 MW figure is the strongest national starting point, while the roughly 1,050 MW Ontario figure is our sum of named operating projects.